water could be drawn off.  The water in the foundation-pit at this time measured about two feet in depth, on an area of forty-two feet in diameter, and yet it was drawn off in the course of about half an hour.  After this the artificers commenced with their picks and continued at work for two hours and a half, some of the sailors being at the same time busily employed in clearing the foundation of chips and in conveying the irons to and from the smiths on the beacon, where they were sharped.  At eight o’clock the sea broke in upon us and overflowed the foundation-pit, when the boats returned to the tender.

[Thursday, 7th July]

The landing-master’s bell rung this morning about four o’clock, and at half-past five, the foundation being cleared, the work commenced on the site of the building.  But from the moment of landing, the squad of joiners and millwrights was at work upon the higher parts of the rock in laying the railways, while the anvils of the smith resounded on the beacon, and such columns of smoke ascended from the forges that they were often mistaken by strangers at a distance for a ship on fire.  After continuing three hours at work the foundation of the building was again overflowed, and the boats returned to the ship at half-past eight o’clock. the masons and pickmen had, at this period, a pretty long day on board of the tender, but the smiths and joiners were kept constantly at work upon the beacon, the stability and great conveniency of which had now been so fully shown that no doubt remained as to the propriety of fitting it up as a barrack.  The workmen were accordingly employed, during the period of high-water, in making preparations for this purpose.

The foundation-pit now assumed the appearance of a great platform, and the late tides had been so favourable that it became apparent that the first course, consisting of a few irregular and detached stones for making up certain inequalities in the interior parts of the site of the building, might be laid in the course of the present spring-tides.  Having been enabled to-day to get the dimensions of the foundation, or first stone, accurately taken, a mould was made of its figure, when the writer left the rock, after the tide’s work of this morning, in a fast rowing-boat for Arbroath; and, upon landing, two men were immediately set to work upon one of the blocks from Mylnefield quarry, which was prepared in the course of the following day, as the stone-cutters relieved each other, and worked both night and day, so that it was sent off in one of the stone-lighters without delay.

[Saturday, 9th July]