“In order to carry out this vast work (the construction of the tubes), eighty houses have been erected for the accommodation of the workmen, which, being whitewashed, have a peculiarly neat and picturesque appearance; among them are seen butcher’s, grocer’s, and tobacconist’s shops, supplying the wants of a numerous population. A day school, Sunday school, and meeting-house also conspicuously figure. Workshops, steam-engines, store-houses, offices, and other buildings meet the eye at every turn; one is led to conclude that a considerable time has elapsed since the works were commenced, yet it is little more than two years ago. A stranger, on coming to the ground, is struck with wonder when for the first time he obtains a near view of the vast piles of masonry towering majestically above all the surrounding objects—strong as the pillars of Hercules, and apparently as endurable—his eyes wander instinctively to the ponderous tubes, those masterpieces of engineering constructiveness and mathematical adjustment; he shrinks into himself as he gazes, and is astonished when he thinks that the whole is the developed idea of one man, and carried out, too, in the face of difficulties which few would have dared to encounter.”
FLOATING OF THE TUBES.
The tubes were floated to the places whence they were elevated to their positions on eight huge pontoons, fitted with valves and pumps to exhaust the water from them, when all was ready to float the prodigious iron beams. These pontoons or boxes were each 90 feet long, 25 feet wide, and 15 feet deep. The pontoons having been placed under one of the tubes (sections), the floating was easily effected, and the operation is thus described by the “Assistant Engineer.”
“The operation of floating the tubes (the four sections, and one only at a time), will be commenced by closing the valves in the pontoons at low water; as the tide rises, the pontoons will begin to float, and shortly afterwards to bear the weight of the tube, which will at last be raised by them entirely off its temporary supporting piers; about an hour and a half before high water, the current running about four miles an hour, it will be dragged out into the middle of the stream, by powerful capstans and hawsers, reaching from the pontoons at each end, to the opposite shore. In order to guide it into its place with the greatest possible certainty, three large hawsers will be laid down the stream, one end of two of them being made fast to the towers (piers) between which the tube is intended to rest, and the other to strong fixed points on the two shores, near to and opposite the further end of the tube platforms; in their course, they will pass over and rest upon the pontoons, being taken through ‘cable-stoppers’ which are contrivances for embracing and gripping the hawser extended across the stream, and thereby retarding, or if necessary entirely destroying, the speed induced by the current.”