room with a plate on each side of the south wall
and one on each side of the wall on the north side
of the center room. The contractors have deviated
from these requirements in having extended the said
brace through the entire length of the building
and placed the plates that were specified for the
north wall of the center room on the respective
sides of the extreme north wall of the building.
While this deviation adds nothing to the security
of the south wall, it is doubtless as effective
as it would have been had it been placed as contemplated
in the plan. It may in some degree strengthen
the north wall, and I recommend that it be accepted
as in compliance with the terms of the contract.
The two iron rods called for in the specifications
are of wrought iron 11/2 inches in diameter, secured
by boiler-iron plates three-eighths of an inch thick
and 12 inches in diameter, securely fastened as
required in the specifications. There was a
necessary deviation from the plan as to the place the
rod nearest the east side of the building should
be placed. Early in the prosecution of the
work a portion of the debris in contact with the eastern
wall was removed. During the night following this
a section of the south end of the east wall fell,
carrying with it that portion of the wall between
the south and east rooms to which the plan required
said rod to be attached. In consequence the contractors
placed the rod so as to connect it with the portion
of the wall still intact. As a brace to the
south wall it is placed advantageously. In
excavation, underpinning, and filling in the contractors
have exceeded the limitations prescribed in the contract,
and have therefore performed an amount of work for
the remuneration of which there is no provision.
The following table shows the amount of work authorized
in each of the four items with reference to which
the contract was drawn and the amount actually performed
by contractors:
Item |1. Excavating and clearing out debris. | |2. Underpinning walls. | | |3. Filling in cavities. | | | |4. Braces. ----------------------+-----------+-----------+------------+
-----------+ Maximum authorized | 350 cubic | 750 cubic | 825 | 1 wood | | yards | feet | cubic feet | and 1 iron| | | | | | Performed by | 570 cubic | 919 cubic | 1,161 | 1 wood and| contractors | yards | feet | cubic feet | 2 iron | | | | | | Excess | 220 cubic | 169 cubic | 336 | | | yards | feet | cubic feet | | | | | | | Contract Price | 60 cents | $1 per | $1 per | $200 | | per cubic | cubic foot| cubic foot | | | yard | | | | | | | | |