was loaded to 900 lb. per sq. ft., at which load no
measurable deflection was apparent. The writer
wished to test it still further, but there was not
enough cement—the material used for loading.
The load, however, was left on for 48 hours, after
which, no sign of deflection appearing, not even an
incipient crack, it was removed. The total area
of loading was 14 by 20 ft. The beam was continuous
at one end only, and the slab only on one side.
In other parts of the structure conditions were better,
square panels being possible, with reinforcement both
ways, and with continuity, both of beams and slabs,
virtually in every direction, end spans being compensated
by shortening. The method of reinforcing was as
before indicated. The enormous strength of the
structure, as proved by this test, and as further
demonstrated by its use for nearly two years, can
only be explained on the basis of the continuity of
action developed and the great stiffness secured by
liberal stirruping. Steel was provided in the
middle section according to the rule, (
w l)/8,
the span being taken as the clear distance between
the supports; two-thirds of the steel was bent up
and carried across the supports, in the case of the
beams, and three-fourths of the slab steel was elevated;
this, with the lap, really gave, on the average, four-thirds
as much steel over the supports as in the center,
which, of course, was excessive, but usually an excess
has to be tolerated in order to allow for adequate
anchorage. Brackets were not used, but extra
horizontal reinforcement, in addition to the regular
horizontal steel, was laid in the bottom across the
supports, which, seemingly, was satisfactory.
The columns, it should be added, were calculated for
a very low value, something like 350 lb. per sq. in.,
in order to compensate for the excess of actual live
load over and above the calculated load.
This piece of work was done during the winter, with
the temperature almost constantly at +10 deg. and
dropping below zero over night. The precautions
observed were to heat the sand and water, thaw out
the concrete with live steam, if it froze in transporting
or before it was settled in place, and as soon as
it was placed, it was decked over and salamanders
were started underneath. Thus, a job equal in
every respect to warm-weather installation was obtained,
it being possible to remove the forms in a fortnight.
[Illustration: PLATE IV, FIG. 1.—SLAB
AND BEAM REINFORCEMENT CONTINUOUS OVER SUPPORTS.
SPAN OF BEAMS = 14 FT. SPAN OF SLABS = 12 FT.
SLAB, 6 IN. THICK.]
[Illustration: PLATE IV, FIG. 2.—REINFORCEMENT
IN PLACE OVER ONE COMPLETE FLOOR OF STORAGE WAREHOUSE.
SLABS, 14 FT. SQUARE. REINFORCED TWO WAYS.
NOTE CONTINUITY OF REINFORCEMENT AND ELEVATION OVER
SUPPORTS. FLOOR DESIGNED FOR 150 LB. PER
SQ. FT. LIVE LOAD. TESTED TO 900 LB.
PER SQ. FT.]